A few commuters have been asking me what has been happening with the Mount Druitt Car Park as it halted for a while and there was no notification sent by Transport for NSW to the local newspapers or even to us, until today, when I made a call:
Yes, I rang the old TCA (Transport Construction Authority phone number), switch lady called Alex transferred to Julieann Marino EA (Executive Assistant) to John Templeton, Manager of programs then transferred to Katie Brennan Public Affairs & Communications Manager. This is where I was explained why Mount Druitt has gone slow for building of the Commuter Car park.
So here it is: the previous construction project managers went bust, as did ''Kel & Rigby Investments Holdings Pty Ltd' and it took time to locate another construction project manager called Structus Group'. I was told concrete is pouring everything is moving and that it is expected to be completed by August this year.
Yes, I rang the old TCA (Transport Construction Authority phone number), switch lady called Alex transferred to Julieann Marino EA (Executive Assistant) to John Templeton, Manager of programs then transferred to Katie Brennan Public Affairs & Communications Manager. This is where I was explained why Mount Druitt has gone slow for building of the Commuter Car park.
So here it is: the previous construction project managers went bust, as did ''Kel & Rigby Investments Holdings Pty Ltd' and it took time to locate another construction project manager called Structus Group'. I was told concrete is pouring everything is moving and that it is expected to be completed by August this year.